November 04, 2019
|
|
MTA Opens New Entrance at 1 Av L Station, Announces Early Completion of Street Restoration on 14th Street |
|
New Station Entrances are Part of L Project Capacity Improvements
Majority of 14th Street Sidewalk Restoration due to L Project Work to be Completed More Than Six Months Early
The Metropolitan Transportation Authority (MTA) today announced two L project milestones with the 1 Av station entrance at Avenue A south now open to the public and the majority of work on the 14th Street sidewalk restoration expected to be completed more than six months ahead of schedule.
“The Project started as a post-Sandy resiliency project, but it has now grown to include much more, with capacity and accessibility improvements along the and other subway lines. We hit yet another positive milestone today with the opening of the first of two new station entrances at 1 Av,” said MTA Chief Development Officer Janno Lieber. “We’re ahead of schedule for the entire project, and it’s satisfying when customers can reap the benefits as the job advances. And thanks to the revised construction approach, we’re getting all this work done without impacting service for the vast majority of the L Train’s 300,000 daily riders.”
The Project encompasses the rehabilitation of the Canarsie Tube, which carries trains between Brooklyn and Manhattan and was severely damaged during Superstorm Sandy. The project also includes new power infrastructure to support train service, several station improvement projects to increase public space and accessibility at stations on the line and several lines that provide alternate subway service during the project. The tunnel rehabilitation, which began in April 2019 using a modified 15- to 18-month construction plan that preserves regular subway service for 90 percent of riders, is currently months ahead of schedule and set to finish in 12 months. In addition to an early construction timeline for the tunnel work, several related construction projects are also ahead of schedule, including the capacity improvement projects at 1 Av and sidewalk restoration on 14th Street.
Nearly 21,000 weekday customers will benefit from the increased capacity at 1 Av, which has seen significant ridership growth of 60 percent from 2000 to 2018. The Project improvements at 1 Av include:
The revised construction schedule at 1 Av was designed to open the new entrances with temporary finishes as soon as they are ready, then close the original entrances for reconstruction in a phased schedule. Two entrances will be open at all times at the 1 Av station. With the opening of the new entrance at Avenue A south, the First Avenue south entrance will close for reconstruction next week. The phasing schedule is as follows:
While the First Avenue south entrance is closed, Brooklyn-bound customers are advised to:
During Weekdays:
During Weekends: At all times, enter at First Avenue north side
Once the Avenue A north entrance is opened and the First Ave north entrance is closed, customers are advised to use both the Avenue A entrances as alternatives.
Schedule for 14th Street restoration:
Under the original plan, street restoration was expected to be completed in May 2020. Under the early timeline, the majority of street restoration activities will be completed at Avenue A by January 2020 and work zones reduced to limited areas like the elevators and First Ave entrances.
Phasing schedule for 14th Street restoration includes:
Work zone 1 (north side of 14th Street, east of First Avenue): Sidewalk restoration completed by mid-August 2019; street restoration currently underway and on track to be completed by January 2020.
Work zone 2 (northwest corner of 14th Street and Avenue A): New entrance and new elevator
Work zone 3 (southwest corner of 14th Street and Avenue A): New entrance and new elevator
Work zone 4 (northwest corner of 14th St and Avenue B): New substation
Customer and pedestrian signage will be available on-site ahead of this work. For more information about the Project and the work planned for the 1 Av station, visit https://new.mta.info/l-project.
|
|
###
|