STATE OF NEW YORKPublic Service Commission Garry A. Brown, ChairmanThree Empire State Plaza, Albany, NY 12223
Further Details: James Denn
James.denn@dps.ny.gov | 518.474.7080
13021/10-T-0139 April 18, 2013
|
|
Commission Approves Major New Power LineNew York City Consumers Would Benefit from Low-Cost Canadian Hydropower |
|
The New York State Public Service Commission (Commission) today approved the construction and operation of a 1,000 megawatt (MW) transmission line stretching 330 miles from the Canadian border to Astoria, Queens, primarily through Lake Champlain and the Hudson River, with some segments on land, primarily in railroad or state highway rights-of-way. The line would terminate at a converter station located in Consolidated Edison’s Astoria annex. From there, one high voltage, alternating current (HVAC) circuit will connect, via underground conduit, to the nearby substation of the New York Power Authority (NYPA). From the NYPA substation, another set of HVAC cables would be located under the streets for about three miles to Con Edison’s Rainey substation. The transmission line, estimated by the developer to cost $2 billion, would be built either underwater or underground along the entire length of the route, avoiding or minimizing visual and other potential environmental impacts. “With this order, we grant the developer a certificate to construct and operate a transmission project known as the Champlain Hudson Power Express Project,” said Commission Chairman Garry Brown. "The certificate will adopt most of the terms and conditions presented to us in a joint proposal and in stipulations that have the full or partial support of a wide range of parties to this case." A critical factor in the Commission’s decision to approve the project is the fact that the financial risk to ratepayers is minimized since ratepayers will not be required to assume the financial risks to build the project; ratepayers will be protected from construction and operation costs. While the Commission’s decision represents a major step to build the privately funded transmission line, it is not the final step; project developers still need to obtain several Federal permits, as well as secure private financing. The project owners, Champlain Hudson Power Express, Inc. and CHPE Properties, Inc., applied for a certificate of environmental compatibility and public need for the siting of major utility transmission facilities to construct and operate the high voltage, direct current transmission line under Article VII of the Public Service Law. The regulatory review of the project under Article VII was rigorous and complete. In addition to providing renewable energy and shielding ratepayers, the project offers other significant benefits:
The proceeding began with an application filed March 30, 2010 and, after several supplements, ultimately deemed compliant as of August 11, 2010. Negotiations among the parties resulted in the joint proposal filed in February 2012 and further stipulations in June, July and October 2012. The joint proposal used as the basis for the Commission’s decision was supported by several state agencies, the cities of New York and Yonkers, Consolidated Edison, and several environmental organizations, including Riverkeeper, Inc. and Scenic Hudson, Inc. Changes in the route from what was initially proposed helped reduce environmental impact. Full evidentiary hearings were conducted on the joint proposal in July 2012, followed by post-hearing briefs. There were two rounds of public statement hearings conducted along the route of the project, both early in the case and following the submission of the joint proposal, and members of the public have submitted written comments as well. The Commission’s decision today, when issued, may be obtained by going to the Commission Documents section of the Commission’s Web site at www.dps.ny.gov and entering Case Number 10-T-0139 in the input box labeled "Search for Case/Matter Number." Many libraries offer free Internet access. Commission orders may also be obtained from the Commission’s Files Office, 14th floor, Three Empire State Plaza, Albany, NY 12223 (518-474-2500). If you have difficulty understanding English, please call us at 1-800-342-3377 for free language assistance services regarding this press release. |
|
###
|