November 15, 2019

LIRR Completes Bridge Installations in East Hampton On Schedule

North Main Street and Accabonac Road New Overpass Height Improves Safety for Passing Vehicles

MTA Long Island Rail Road today announced it has completed replacement of two 124-year-old bridges in East Hampton on time, raising their heights to reduce truck strikes.

The two bridges, at North Main Street and Accabonac Road, are separated by about 500 feet and were built in 1895. The North Main Street Bridge is the westernmost bridge and had a posted clearance of 10 feet. The Accabonac Road Bridge, the easternmost bridge, had a posted clearance of 9 feet 9 inches. The LIRR raised the vertical roadway clearance to 14 feet with the installation of new single span steel bridge structures. The new height clearance allows trucks to safely pass underneath the bridges. In 2015, there were nine incidents in which vehicles struck the overpasses, reiterating the need to improve safety and reliability for both vehicles and LIRR passengers by replacing them.

“These bridge replacements exemplify how the LIRR is improving safety across the system and reliability of service on LIRR, and also improving the quality of life for neighboring communities,” said LIRR President Phil Eng. “I commend our crews, who worked efficiently to complete this complex project on schedule. As we have elsewhere on the Island, our staff worked with the community throughout the project to provide updates, answer questions, and seek feedback that could help us reduce any impacts.”

“The Village of East Hampton is thankful to the LIRR and the State Legislature for ensuring this important project came to fruition and has been completed in a timely fashion,” said East Hampton Village Mayor Paul Rickenbach, Jr. “Increasing motorist safety on the roads and passengers traveling on the LIRR is of the utmost importance. We firmly believe this project will provide those results. While I am taking this moment to thank the State, I also want to thank the area residents and businesses for their patience and cooperation during each phase and especially during the major construction. The Village greatly appreciates their understanding. My colleagues and I are pleased to support the LIRR with the completion of this considerable capital improvement.”

"The completion of the two new bridge overpasses on the Montauk branch in the Village of East Hampton provides another example of the continued partnership between the LIRR and the East End community to improve safety and service for our residents and visitors. The addition of the wildly successful South Fork Commuter Connection, the modernization of the East Hampton train station, and today's completion of these bridge projects, demonstrates the LIRR's commitment to improving public transit on the East End. Today's announcement regarding the completion of the bridges specifically marks an improvement in safety at locations where motor vehicle accidents were all too common. I look forward to continued capital investment by the LIRR to insure viable public transit in the future,” said Assemblyman Fred W. Thiele, Jr.

"I am very proud to attend an event that highlights what our hardworking in-house engineering workers accomplish day in and day out to make our system stronger and safer.  While union workers may be portrayed in a negative light at times, recognizing the accomplishments they achieve is a well-deserved pat on the back. On behalf of our organization I want to personally say thank you to our members for always stepping up and delivering day in and day out," Sheet Metal Air Rail Transportation (SMART) General Chairman Anthony Simon said.

Construction activities for this project began in August 2018 with work on the 4 retaining walls taking place in the fall of 2018. The two walls east of Accabonac Road Bridge along the north and south rights-of-way were completed first along with the north wall between the bridges, which is also along the north and south right-of-way. The fourth wall, located along the south side of the tracks between the two bridges and parallel to Hook Mill Road was completed soon after. The installation of 8 caissons, watertight retaining structures that are filled with concrete, began in June 2019 and were completed in October.

The LIRR Structures Department removed and demolished the old bridges mid-October - first with the Accabonac Road bridge and then the North Main Street bridge. The large bridge components, which were fabricated in Lancaster, PA, were transported from Pennsylvania by road, then via barge through the Long Island Sound, around the tip of Orient Point, through the North and South Forks to Shinnecock Inlet, then via road again to East Hampton, where the East Hampton Station Enhancement was completed April 2019.

About East Hampton Station Modernization

The 125-year-old station, located on Railroad Avenue between Newtown Lane and Race Lane, received several station enhancements including a restoration on its historic brick façade. Since 2000, the station has been on the National Register of Historic Places. In keeping with the station’s history, the interior charm has been preserved with repairs of wood paneling and notable photos of the station are on display in the customer waiting area.

In modernizing the station, enhancements include new LED lighting on platform areas, installation of bulletin boards, CCTV security cameras, as well as a heating system and restrooms.  The station plaza has been improved to include benches, bike racks and digital information totems.

Fun Facts About the East Hampton Bridges

  • Each bridge weighs 175 tons
  • The total ballast is 5,500 tons
  • Tracks were raised 34 inches to accommodate the work
  • The project used 3 cranes with booms measuring 180 feet
  • 2 drilling rigs were used during the construction drilling to a depth of 90 to 120 feet
  • Each of the 8 bridge caissons contains 120 yards of concrete
  • During the year the bridges and station were originally constructed (1895), Grover Cleveland was in his second term as president and Guglielmo Marconi has transmitted radio signals for about 1.5 miles

The bridge replacements are part of the broader LIRR Modernization Program, with 100 projects across the railroad, to improve the overall LIRR system efficiently and reliably. For more information on LIRR’s capital projects, visit amodernli.com

###
MTA New York City Transit • MTA Long Island Rail Road • MTA Metro-North Railroad • MTA Bridges and Tunnels • MTA Construction & Development • MTA Bus Company • MTA Police Department

2 Broadway
New York, NY 10004
Media Contact: (212) 878-7440


This message was sent by the Metropolitan Transportation Authority (MTA) press release distribution system. If you would like to customize which agencies you receive communications from, stop receiving emails, or discontinue receiving emails from the MTA altogether, please manage your preferences or unsubscribe at this link: manage your preferences or unsubscribe.

Copyright © 2024 New York State. All rights reserved. | Our Privacy Policy