July 22, 2020

MTA Announces Accelerated Accessibility Projects for Bronx Subway Complex and Station

New Projects Will Bring Elevators and Other ADA Features to 149 St-Grand Concourse 245 Complex and Tremont Av bd Station

MTA Bundling Projects and Taking Advantage of Lower Ridership During Pandemic to Shorten Construction Schedule and Lower Cost

The Metropolitan Transportation Authority (MTA) Board voted today to approve a contract to bring full accessibility to a major station complex and an additional station in the Bronx, with officials bundling the projects and taking advantage of lower ridership during the COVID-19 pandemic in order to shorten the construction schedule and lower cost. The projects will bring elevators and other ADA features to the 149 St-Grand Concourse complex on the 245lines and the Tremont Av station on the bd line in the Bronx.

“This contract reflects our commitment to ADA and to making our system more accessible as quickly as possible,” said MTA Construction & Development President Janno Lieber. “We’re taking advantage of synergies between the two projects, and the current lower ridership, to deliver these projects faster and cheaper – a win-win for the MTA and our customers.”

“Making this station complex and station accessible brings us closer to our immediate goal of ensuring that no one is ever more than two stops away from an accessible subway station,” said Alex Elegudin, NYC Transit Senior Advisor for Systemwide Accessibility. “The 149 St-Grand Concourse project will be particularly helpful for the many students of nearby Hostos Community College. The MTA is working hard to expand accessibility and these projects are a huge step in that direction.”

The projects will feature design-build services in order to draw from innovation, enhance efficiency, and minimize duration, cost and disruption to customers, and will include:

  • At 149 St-Grand Concourse, a three-stop elevator connecting the street, upper platform, and lower mezzanine, as well as two elevators connecting the upper platform, lower mezzanine, and lower platform.
  • At Tremont Av, one street-to-mezzanine elevator and two mezzanine-to-platform elevators.
  • Reconstruction of stairs to current ADA standards.

Construction on both projects is expected to begin in approximately three months after a preliminary design stage. The Tremont Av project is expected to take 24 months and the 149 St-Grand Concourse project is expected to take 35 months. The stations are expected to remain open during the project. The MTA was able to negotiate for a shortened construction schedule and a favorable price by moving the work forward while ridership is down due to the COVID-19 pandemic.

The $93.2 million contract will be awarded to Tully Construction Company Inc. and includes an early completion incentive for reductions to the project duration and liquidated damages for extended durations resulting from contractor delays.

Work schedules and service plans will be determined and announced after a preliminary planning stage. The MTA will work closely with the contractor and local community to minimize disruption to customers and neighbors.

###
MTA New York City Transit • MTA Long Island Rail Road • MTA Metro-North Railroad • MTA Bridges and Tunnels • MTA Construction & Development • MTA Bus Company • MTA Police Department

2 Broadway
New York, NY 10004
Media Contact: (212) 878-7440


This message was sent by the Metropolitan Transportation Authority (MTA) press release distribution system. If you would like to customize which agencies you receive communications from, stop receiving emails, or discontinue receiving emails from the MTA altogether, please manage your preferences or unsubscribe at this link: manage your preferences or unsubscribe.

Copyright © 2024 New York State. All rights reserved. | Our Privacy Policy